Below you can find the kluslijst van Jaffa for the klusseizoen 2023-2024. The jobs are grouped by klusploeg, the order of jobs is random.
Goals for this year:
- Paint Interior
- Remount windows
- Solve leaks and water movement through the boat
- Overhaul kitchen
Priority:
- Needs to be done in the maintenance season
- Preferably done during the maintenance season
- Could be done in the sailing season
- Can be posponed to the next maintenance season
- We can also leave this be
Feel free to add jobs and request budget.
Vul boodschappen voor de matco-ning of als voorbereiding op een klusweekend hier in, of zet het in de loods op het verlanglijstje.
Overview
Colour coding of the first column: green = finished, orange = job has been started, but isn't finished yet. Hopefully there is a remark stated at the job description.
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spend
|
Remarks
|
Rigging-01 |
Controleren Mast
|
1 |
€ |
|
|
€ |
|
Rigging-02 |
Klemmen controleren
|
1 |
€ |
|
|
€ |
|
Rigging-03 |
Lijnen controleren
|
1 |
€ |
|
% |
€ |
|
Rigging-04 |
Lieren schoonmaken en vetten (Zie klusdraaiboek Jaffa)
|
1 |
€ |
|
|
€ |
|
Rigging-05 |
Blokken controleren
|
1 |
|
|
|
€ |
|
Rigging-06 |
Lijnen wassen
|
1 |
€ |
|
% |
€ |
|
Rigging-07 |
Zeilen controleren
|
1 |
€ |
|
|
€ |
Genua en GZ waarschijnlijk worden (waarschijnlijk) vervangen.
|
Rigging-08 |
[job name]
|
1 |
€ |
|
|
|
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Engine-01 |
Standaardonderhoud (zie: Algemene gegevens Motor)
|
1 |
€ |
|
% |
€ |
|
Engine-02 |
Gas- en keerkoppelingskabel nakijken
|
1 |
€ 0 |
|
0% |
€0 |
|
Engine-03 |
Nieuwe motorsteunen bestellen
|
1 |
€ 0 |
Romke |
0% |
€0 |
|
Engine-04 |
Motor opnieuw laten uitlijnen
|
1 |
€ 0 |
Romke |
0% |
€0 |
Werf uitzoeken en offerte laten maken voor installeren nieuwe steunen en uitlijnen
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE-01 |
Schoonmaakazijn in de WC-pomp zuigen om aanslag los te weken
|
3 |
€ |
|
0% |
€ |
|
GWE-02 |
Verlichting binnen controleren
|
3 |
€ |
|
% |
€ |
|
GWE-03 |
Handleiding wc schrijven
|
5 |
€ |
|
0% |
€ |
|
GWE-04 |
Alle afsluiters controleren (schroeven op wc-afsluiters losdraaien!)
|
1 |
€ |
|
% |
€ |
|
Gwe-05 |
Fix grounding of the keel!!!
|
1! |
€ |
|
0% |
€ |
The keel needs to be connected to the negative terminal of the electric system, as well as the mast in order to provide protection against lightning strikes
|
GWE-06 |
Bilgepompen controleren op werking
|
1 |
€ |
|
0% |
€ |
|
GWE-07 |
Besluit nemen over wel/niet behouden van de halo.
|
3 |
€ |
|
0% |
€ |
|
GWE-08 |
Navtex: opnieuw aansluiten.
|
3 |
€ |
|
0% |
€ |
|
GWE-09 EPIRB |
Check EPIRB battery and get checked/replaced if out of date.
|
3 |
€ |
|
0% |
€ |
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior-01 |
1 |
€ |
|
% |
€ |
|
Interior-02 |
Regenpijpen keuken herzien.
|
1 |
€ |
|
% |
€ |
Nieuwe buizen maken voor mokken. De huidige laten krassen achter op de mokken. Buis voor soepkommen kan eventueel verwijderd. Soepkommen worden nooit gebruikt.
|
Interior-03 |
Matrassen mossel vervangen.
|
5 |
€ |
|
% |
€ |
|
Interior-04 |
SB zakken vervangen.
|
4 |
€ |
|
% |
€ |
Geschikt materiaal moet worden gezocht.
|
Interior-05 |
Gordijn WC
|
2 |
€ |
|
% |
€ |
Gordijntje maken voor de doorgang naar het vooronder.
|
Interior-06 |
Gat maken in voorste bilge onder WC.
|
1 |
€ |
|
% |
€ |
Vraag Romke voor instructies.
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior-01 |
Apply new coat of antifouling
|
1 |
€ |
|
% |
€ |
|
Exterior-02 |
Replace red tape on the waterline
|
2 |
€ |
|
% |
€ |
|
Exterior-03 |
Bevestiging kiel controleren (Check keel mount)
|
1 |
€ |
|
% |
€ |
|
Exterior-04 |
Replace dyneema lashings for lifelines/jackstays and clipping line
|
1 |
€ |
|
% |
€ |
measurements. extra small: 75 cm. 2 smalls: #1 total 185cm 2# total 186 cm. Large: #1 total 710.4 cm #2 total 710.4 cm
|
Exterior-05 |
Replace griptape on the tiller
|
3 |
€ |
|
% |
€ |
|
Exterior-06 |
Check lifelines/jackstays
|
1 |
€ |
|
50% |
€ |
Zijn nog goed. Terugplaats.
|
Exterior-07 |
Solve sliding of the railing cushions
|
3 |
€ |
|
0% |
€ |
|
Exterior-08 |
Iemand met verstand laten kijken naar de deuken in het dek voor de mast
|
2 |
€ |
|
0% |
€ |
|
Exterior-09 |
Fix leaking companionway hatch
|
2 |
€ |
|
% |
€ |
Replace foam tape
|
Exterior-10 |
Build a better stopping solution for sliding hatch
|
3 |
€ |
|
% |
€ |
Have the end-caps printed in metal or similar
|
Exterior-11 |
Repaint the topsides
|
2 |
€ |
|
% |
€ |
|
Exterior-15 |
New linebags
|
3 |
€ |
|
% |
€ |
tijdens zeilseizoen naar kijken
|
Exterior-16 |
Fixate stanchions SB
|
2 |
€ |
|
% |
€ |
|
Windows |
Re-mount windows
|
1 |
€ |
Kasper,Hylke |
% |
€ |
DIT MOET AF IN WEEK 17!!!
|
Exterior-18 |
Repair storm-damage aft starboard
|
2 |
€ |
Rolf,Romke |
80% |
€ |
I filled the majority of the holes, but I'll need to touch it up once it has dried, and then it'll need to be coated. Alle deuken zijn geplamuurd geschuurd geplamuurd enzovoorts enzovoorts. Alleen nog schilderen.
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inven-01 |
Check life raft
|
1 |
€ |
Romke, Thimo |
80% |
€ |
Is weggebracht naar de dealer. Naar verwachting voor april klaar. Is gecheckt en komt 23 april naar Enschede.
|
Inven-02 |
Check grab bag
|
3 |
€ |
|
90% |
€ |
NODIG:
|
Inven-03 |
Check first aid box and medication box
|
1 |
€ |
|
90% |
€ |
Missing from pillbox
- Primatour - Niet Aanwezig
- ORS 24 tabletten - Niet Aanwezig
- Norit 200 - Niet Aanwezig, alleen Imodium (2mg loperamide)
- Loratidine Hooikoortstabletten - Niet Aanwezig
- Paracetamol+coffeine - Niet Aanwezig, alleen puur paracetamol 500mg, en Ibuprofen 200mg
Missingfrom F/Aid box:
- Safety pins - Niet Aanwezig, wel andere verband pins met elastiek
|
Inven-04 |
Update important documents binder
|
1 |
€ |
|
90% |
€ |
Ship station license + orc certificaat moet nog
|
Inven-05 |
Reserveonderdelen motor voor aan boord tijdens seizoen
|
1 |
€ |
Kasper |
0% |
€ |
|
Inven-06 |
Check life vests for leaks and firing mechanism
|
1 |
€ |
Tiemen |
% |
€ |
Reddingsvesten voor controleren oppompen en niet opblazen i.v.m. vocht. Checken op goed vastzitten van de gascilinder en aanwezigheid van kruisbanden. Ook houdbaarheidsdatum patronen checken en kijken of er genoeg reservepatronen zijn. Lekke vesten direct markeren en weggooien! Nieuwe vesten moeten voorzien zijn van een lampje en sprayhood.
|
Inven-07 |
Check Dan Buoy for leaks
|
1 |
€ |
|
% |
€ |
|
Inven-08 |
Clean cable cutter and grease hinges
|
2 |
€ |
|
% |
€ |
|
Inven-09 |
Check EPIRB
|
1 |
€ |
Romke |
% |
€ |
|
Inven-10 |
Check tethers for chafing and wear
|
1 |
€ |
|
% |
€ |
|
Inven-11 |
Check pyrotechnics (Best before date and quantity)
|
1 |
€ |
|
% |
€ |
|
Inven-12 |
Check fire extinguishers certification
|
1 |
€ |
|
% |
€ |
|
Inven-13 |
Update charts
|
3 |
€ |
|
% |
€ |
|
Inven-14 |
New toolbox. Check all toolboxes on whether they are still ok.
|
3 |
€ |
|
% |
€ |
|
Begroting
Post |
Budget |
Wat we nu willen |
|
Uitgegeven
|
Algemeen |
|
|
|
|
Rigging |
|
|
|
|
Engine |
|
|
|
|
GWE |
|
|
|
|
Interior |
|
|
|
|
Exterior |
|
|
|
|
Inventory |
|
|
|
|
Loods algemeen |
|
|
|
|
(Reservering) Grote uitgave |
|
|
|
|
Vaarseizoen |
|
|
|
|
Onvoorzien |
|
|
|
|
Totaal |
3500 |
|
|
|
Inventory
Actuele voorraad: Media:Vuurwerk_jaffa.xls.
Nodig volgens reglementen (OSR3):
soort vuurwerk |
aantal
|
Rode Parachutes |
niet verplicht
|
Rode Handflares |
4
|
Oranje Rookpotten |
2
|
Witte Handflares |
niet verplicht
|
During the sailing season
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Next maintenance season
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Jobs for next time
- Test/repair Navtex
- Repaint the rear berths and the nav table white
- Paint/sticker the waterline
- Toilet curtain