|
|
Regel 295: |
Regel 295: |
|
| |
|
| | style="background:orange" | [[#Inven-06|Inven-06]] || Check life vests for leaks and firing mechanism | | | style="background:orange" | [[#Inven-06|Inven-06]] || Check life vests for leaks and firing mechanism |
| |1||€ || ||75% ||€ || Need to be recharged | | |1||€ || ||75% ||€ || Need to be rearmed |
| |- | | |- |
|
| |
|
Below you can find the kluslijst van Jaffa for the klusseizoen 2018-2019. The jobs are grouped by klusploeg, the order of jobs is random.
Priority:
- Needs to be done in the maintenance season
- Preferably done during the maintenance season
- Could be done in the sailing season
- Can be posponed to the next maintenance season
- We can also leave this be
Feel free to add jobs and request budget.
Vul boodschappen voor de matco-ning of als voorbereiding op een klusweekend hier in, of zet het in de loods op het verlanglijstje.
Overview
Colour coding of the first column: green = finished, orange = job has been started, but isn't finished yet. Hopefully there is a remark stated at the job description.
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spend
|
Remarks
|
Rigging-01 |
Checking the mast
|
1 |
€ |
|
% |
€ |
|
Rigging-02 |
Checking all cleats and clutches, overhaul if necessary
|
1 |
€ |
|
50% |
€ 0 |
All checked, Spinlock clutches have been ordered, maybe we need to order new cleats too.
|
Rigging-05 |
Clean and grease the winches (Check klusdraaiboek Jaffa)
|
1 |
€ |
Arthur & Dorien |
50 % |
€ |
Lewmar Winches have been cleaned
|
Rigging-06 |
Check all blocks
|
1 |
€ |
Wouter |
50% |
€ |
Most blocks look okay, cunningham bottom block needs to be replaced (triple fiddle block 29mm) No spare blocks in stock atm, need to be restocked
|
Rigging-08 |
Check sails and send to sailmaker if necessary
|
1 |
€ |
|
50% |
€ |
Spi top, Genua voorlijkpatch & reguleerlijn, Grootzeil patch (bakboord) kunnen we zelf doen
|
Rigging-09 |
Straighten windex
|
1 |
€ |
|
0% |
€ |
|
Rigging-10 |
Replace mast cuff
|
1 |
€ |
Wouter |
50% |
€ |
Has been ordered
|
Rigging-11 |
Replace jib halyard (and reshuffle halyard colours in a more sensible way)
|
2 |
€ |
Wouter |
0% |
€ |
we have a colour scheme for the halyards
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Engine-01 |
Standaardonderhoud (zie: Algemene gegevens Motor)
|
1 |
€ |
Kasper |
0% |
€ |
|
Engine-02 |
Rookprobleem oplossen
|
1 |
€ |
Kasper |
50% |
~€? |
Stoptober
|
Engine-03 |
Uitlijning schroefas nakijken
|
2 |
€ 0 |
Kasper |
0% |
€0 |
|
Engine-04 |
Uitlaatslang vervangen
|
1 |
€ 0 |
Kasper |
0% |
€0 |
Is besteld
|
Engine-05 |
Gas- en keerkoppelingskabel nakijken
|
1 |
€ 0 |
Kasper |
0% |
€0 |
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE-01 |
Schoonmaakazijn in de WC-pomp zuigen om aanslag los te weken
|
3 |
€ |
|
0% |
€ |
|
GWE-02 |
Replace water tubes
|
1 |
€ |
|
0% |
€ |
|
GWE-03 |
Check all navigation lights and replace bulbs if needed
|
1 |
€ |
|
50% |
€ |
Stern light has a loose contact, needs to be fixed
|
GWE-04 |
Make a manual for the toilet
|
3 |
€ |
|
0% |
€ |
|
GWE-05 |
Check all through-hull openings and replace packing in toilet sea-cocks
|
1 |
€ |
Jacco |
50% |
€ |
Vetkoord WC is vervangen, keuken en motor afsluiter moeten nog gevet worden met siliconenvet
|
GWE-06 |
Check water tank and rinse/clean if necessary
|
1 |
€ |
|
0% |
€ |
|
GWE-07 |
Fix grounding of the keel, no connection atm with the rest of the boat/mast
|
1 |
€ |
Wouter |
0% |
€ |
|
GWE-08 |
Replace light in port compass
|
2 |
€ |
Wouter |
0% |
|
A resistor might do the job
|
GWE-09 |
Replace clipper display with B&G
|
1 |
€ |
Jacco & Menno |
50% |
€ |
Hole has been drilled
|
GWE-10 |
Fix toilet cover
|
1 |
€ |
Kasper |
0% |
€ |
|
GWE-11 |
Add silver spoon to the water tank (thrift shop)
|
3 |
€ |
|
0% |
€ |
|
GWE-12 |
Fix autopilot alignment
|
2 |
€ |
|
0% |
€ |
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior-01 |
Check interior lighting and replace if necessary
|
3 |
€ |
|
0% |
€ |
|
Interior-02 |
Finish kitchen
|
1 |
€ |
|
0% |
€ |
|
Interior-03 |
Fix hinges in kitchen
|
1 |
€ |
|
0% |
€ |
|
Interior-04 |
Fix floor planks
|
1 |
€ |
|
0% |
€ |
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior-01 |
Apply new coat of antifouling
|
1 |
€ |
|
0% |
€ |
|
Exterior-02 |
Repaint hull
|
1 |
€ |
|
0% |
€ |
Still waiting on new sanders
|
Exterior-03 |
Bevestiging kiel controleren (Check keel mount)
|
1 |
€ |
Wouter |
100% |
€ |
Done
|
Exterior-04 |
Replace dyneema lashings for lifelines/jackstays and clipping line
|
1 |
€ |
|
0% |
€ |
|
Exterior-05 |
Replace griptape on the tiller
|
2 |
€ |
|
0% |
€ |
|
Exterior-07 |
Solve noises coming from the rudder bearings
|
1 |
€ |
Freddy |
0% |
€ |
New bearings are being placed
|
Exterior-08 |
Check lifelines/jackstays
|
1 |
€ |
|
0% |
€ |
|
Exterior-11 |
Iemand met verstand laten kijken naar de deuken in het dek voor de mast
|
2 |
€ |
|
0% |
€ |
|
Exterior-12 |
Repaint the deck wherever necessary
|
2 |
€ |
Jacco |
25% |
€ |
Deck has been sanded
|
Exterior-12 |
Fix leaking companionway hatch
|
2 |
€ |
|
0% |
€ |
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inven-02 |
Check grab bag
|
3 |
€ |
|
0% |
€ |
|
Inven-03 |
Check first aid box and medication box
|
1 |
€ |
|
0% |
€ |
|
Inven-04 |
Update important documents binder
|
1 |
€ |
|
0% |
€ |
|
Inven-05 |
Reserveonderdelen motor voor aan boord tijdens seizoen
|
1 |
€ |
Kasper |
0% |
€ |
|
Inven-06 |
Check life vests for leaks and firing mechanism
|
1 |
€ |
|
75% |
€ |
Need to be rearmed
|
Inven-07 |
Check Dan Buoy for leaks
|
1 |
€ |
|
0% |
€ |
|
Inven-08 |
Clean bolt cutter and grease hinges
|
2 |
€ |
|
0% |
€ |
|
Inven-09 |
Check EPIRB
|
1 |
€ |
|
0% |
€ |
|
Inven-10 |
Check tethers for chafing and wear
|
1 |
€ |
|
0% |
€ |
|
Inven-11 |
Check pyrotechnics (Best before date and quantity)
|
1 |
€ |
|
0% |
€ |
|
Inven-13 |
Update charts
|
3 |
€ |
|
0% |
€ |
|
Begroting
Post |
Budget |
Wat we nu willen |
|
Uitgegeven
|
Algemeen |
|
|
|
|
Rigging |
700 |
|
|
|
Engine |
150 |
120 |
|
|
GWE |
600 |
|
|
|
Interior |
|
|
|
|
Exterior |
500 |
|
|
|
Inventory |
800 |
|
|
|
Loods algemeen |
|
|
|
|
(Reservering) Grote uitgave |
|
|
|
|
Vaarseizoen |
500 |
|
|
|
Onvoorzien |
|
|
|
|
Totaal |
3500 |
|
|
|
Clarification
General
Rigging
Rigging-03
All clutches have been replaced by Spinlock XAS (4-8mm) or Spinlock XTS (6-10mm). Keep the different sizes in mind when ordering new cams
Engine
Engine-01
Elk jaar moet er standaardonderhoud gepleegd worden, zie voor wat er moet gebeuren en al is gedaan: Algemene gegevens Motor.
Engine-02
De motorboer in Enkhuizen heeft in oktober de verstuivers getest en geconstateerd dat deze slecht waren. Worden voor de terugvaart vervangen en lost hopelijk het rookprobleem en mogelijk de trilling in de schroefas op.
Engine-03
De schroefas trilt flink, vooral bij bepaalde toerentallen. Mogelijk komt dit ook doordat de motor niet helemaal regelmatig liep door de slechte verstuivers, dus nadat die zijn vervangen moet er even gekeken worden of het trillen minder wordt. Als het trillen is gebleven moet er naar de uitlijning worden gekeken. Dit kan alleen goed als de boot op de kant staat, dus dor een professional laten doen is lastig.
GWE
GWE-05
Om de 2 jaar moet het vetkoord van de WC afsluiters vervangen worden om lekkage te voorkomen. Het benodigde vetkoord is vierkant 5mm
GWE-07
The keel needs to be connected to the negative terminal of the electric system, as well as the mast in order to provide protection against lightning strikes
Interior
Exterior
Inventory
Inven-06
Reddingsvesten voor controleren oppompen en niet opblazen i.v.m. vocht. Checken op goed vastzitten van de gascilinder en aanwezigheid van kruisbanden. Ook houdbaarheidsdatum patronen checken en kijken of er genoeg reservepatronen zijn. Lekke vesten direct markeren en weggooien!
Nieuwe vesten moeten voorzien zijn van een lampje en sprayhood, de op het moment voordeligste vesten die hieraan voldoen zijn de Marinepool 300N vesten
Inven-11
Actuele voorraad: Media:Vuurwerk_jaffa.xls.
Nodig volgens reglementen (OSR3):
soort vuurwerk |
aantal
|
Rode Parachutes |
niet verplicht
|
Rode Handflares |
4
|
Oranje Rookpotten |
2
|
Witte Handflares |
niet verplicht
|
Shopping list
Code |
Item |
Supplier |
Price |
Ordered? (Y/N) |
Bought by |
Owner
|
|
- Isolatiedeken (is er nu 1, doe er maar 2 bij? Kost niks doet veel)
|
drogist |
|
N |
|
Hylke
|
|
|
During the sailing season
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Rigging-04 |
Check halyards and other lines (sheets, traveller lines) for wear
|
1 |
€ |
Wouter |
100% |
€ |
Lines have been checked, no replacements needed
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Next maintenance season
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Completed
Rigging
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Rigging-07 |
Wash sheets and lines
|
1 |
€ |
|
100% |
€ |
Sheets and lines have been washed
|
Engine
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
GWE
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Interior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Exterior
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inventory
Code
|
Job
|
Prio
|
Budget
|
Owner
|
% Completed
|
Budget spent
|
Remarks
|
Inven-01 |
Check life raft
|
1 |
€ |
|
100% |
€ |
Is still good
|
Inven-12 |
Check fire extinguishers certification
|
1 |
€ |
|
100% |
€ |
Checked and on board
|
Zie ook